Welcome to my Shack 2.0 Project: Second Part page. If you have missed first one, please, check it at SHACK 2.0: First Part
Well, once workers were gone, I began my work. It was scheduled as:
I hope you enjoy the project evolution. Of course I encourage you to share with me any ideas you could have about this project. Thanks!
73 JOSE EB5AGV
Painting
Populating the repair workbench
Updated pictures of the repair workbench
Here you have some pictures of the painting process... not a very funny thing to do but, well, it is necessary :-)
Painting corners:
First paint layer:
And now, after three layers:
First micro-shack. EB5AGV again ON-AIR :-)!
These are the pictures of the process.
First, all material is ready on the floor:
I neeed to clean all the electrical boxes and flush-cut the tubing:
After some cabling work, I had ceiling lights working!
So now it was time for the 12 x 3 wall power sockets. It took some hours to finish them:
I have put electrical blinds:
For long-term maintenance, it is better to label the cables. These are a couple electrical junction boxes and the current cabling, which includes a by-pass of the old shack installation (which run just below where the old window was). Now all is connected back and working!
I will continue with workbench-level Legrand DLP contour perimeter trunking...
Yes, this is not a typo. After all the painting work, I discovered that paint was of very low quality, not washable and, in fact, water removed it :-(
So, after some hesitation, I decided to repaint at least walls. I gave them two extra layers of TKROM Fortuna M-60 paint, a very good quality paint. So all electrical material went out (at least their covers), covered everything not paintable with tape and went back to paint:
This time, result was again white... BUT durable!
So, a couple days later, I was able to continue with the interrupted electrical installation. I put the Legrand DLP on the wall:
This is the workbench level one:
And this is the lower level one (this will be used mainly for antenna cabling)
This is the main antenna cable entry point:
And this is the pass to the inner shack:
First step was to cut the 20 x 3m metal bars, following my design:
Then I laid out main workbench on the floor. It will be 270 x 120cm:
And then build the thing:
And add on top the (heavy!) wood surface:
The metal frame construction has a big advantage, as you can still acccess the trunking on the walls. Of course, once I begin to fill the lower shelves, it will be harder. But I plan to install needed wiring and then fill the shelves.
I built also a secondary bench, 330 x 80cm:
This is what happens when you try to save time... I had drilled all the wall with an old shelf guide I had... to find that current model had another support scheme. So I needed to add more holes in my new wall:
Luckily, all holes were covered with the guides:
Shelves under construction:
And shelves done!
First thing I installed was my stereo system, mainly comprised of a YAMAHA MX-50 power amplifier and a YAMAHA C-45 pre-amplifier, along an ONKYO T-4670 tuner and a MARANTZ CD-63 CD player. Speakers are RA Labs Mini-Reference. I will add later a DAB tuner and a DVD-player.
I am still waiting for the Legrand DLP acessories so I can't finish the electrical installation yet.
This is a very preliminary setup of my PC in the second bench. Of course, it is just a temporary setup.
As you can see on the floor, I have already passed antenna cabling inside the shack but they are still unconnected and waiting to be routed conveniently using the DLP system.
This is another shelf I built later, in the opposite area to the main workbench. Below it, I will build a mechanical workbench, which will be used for mechanical works.
I have done a change in my initial plans regarding the radio station. I planned to install it in the inner room but have found that the new one was a better place to have it, at least its newer-rigs section, so here it is.
First, I built some over the bench shelves:
And. after some work, here you have a first setup:
I have to trim antenna cables and put them on the Legrand DLP trunking system, but right now the EB5AGV Radio Station is again operative :-)
Finally, I got the rest of electrical materials needed to end the installation so I was able to finish the repair area.
These were the looks just before starting the wire trunking works:
First, I put the supports to check the distribution for the sockets:
After a couple hours working on cabling, I have them ready to fit on the trunking system:
This is a sample of the cabling done:
And then the sockets were put on the trunking:
Later, the covers were put on the sockets:
And finally, trunking covers and socket covers were installed:
And that is all :-)!
So, after the electrical installation was done, it was time to populate the workbench.
This was the old workbench:
And this is the new in process...
First, I put the computer (for size comparison, display is 23"):
Then the soldering station:
Now some test equipment:
And more...
Of course, I will add/remove some items but, finally, I have a working setup :-)
Here you have some April 2010 pictures, showing some additions and slight modifications:
And here you have some August 2010 pictures. I have finally put the definitive lighting:
Page INDEX
Painting
Electrical installation
Painting again!!!
Electrical installation - II
Workbench setup
Populating the radio station
Electrical installation - III
Populating the repair workbench
Updated pictures of the repair workbench
Keep tuned, more to come soon!